If I am requesting to do work in the 100-Foot Buffer Zone, how do I obtain a permit from Conservation?
Category:
Conservation
For small projects located entirely or partially in the 100-foot wetlands buffer zone (but not within 200 feet of a perennially running stream or river) you may submit a Request for Determination of Applicability with a plan sketch or other description of the work to be done, showing any measures you plan to take to protect nearby wetlands from alteration. If the project is determined to have no wetland impact, you will be given permission to proceed as soon as a 10-day appeal period passes.
Updated 6/25/2019 11:10 AM